South Old Corry Field Road Improvements (Bridge Replacement, Sidewalk, & Drainage)

As a result of the April 2014 flooding event, approximately 300' of Old Corry Field Road washed out above and on each side of the existing box culverts at East Jones Creek.

The County installed an open-bottom precast bridge to replace the damaged structure. 

Last Updated: 5/9/2023

BRIDGE REPLACEMENT, SIDEWALKS & DRAINAGE:

  • Construction Start Date: 10/8/18
  • Construction 100% Complete


   

  • Old%20Corry%20Field%20Road%20Aerial%20Map
  • Sidewalk area
  • Old%20Corry%20Field%20Before%20&%20After
  • Picture1
Project Manager:
Office Phone:
850-595-1625
Cell Phone:
850-516-2855
Architect/Engineer:
BRIDGE: Baskerville-Donovan & Contech Engineered Solutions SIDEWALKS: Jehle Engineering
Contractor:
ROADS INC.
District:
District 2
Funded:
Yes
Funding Sources:
L.O.S.T.
Sponsoring Division:
Engineering - Construction Management
Date Completed:
5/5/2020