This project improved drainage conditions within the evaluation area. Drainage improvements were designed for placement within the right-of-way of Chandler Street and Chauncey Street, east of Chandler Street and across the Burlington Northern Railroad Track for connection to the Holsberry Regional Retention Pond. Construction completion date is January 16,02026.
Local Options Sales Tax, State and Federal Grants funded this project.
| Milestone | Date | Notes |
|---|---|---|
| Warranty Completion/Warranty Dates | 1/16/2026 | - 1/16/2028 |
| Construction Final Completion | 1/15/2026 | |
| Construction 75% Complete | 10/15/2025 | Substantial Completion |
| Construction 50% Complete | 8/29/2025 | |
| Construction 25% Complete | 4/4/2025 | |
| Construction Notice to Proceed | 12/11/2024 | |
| Construction Award | 11/7/2024 | |
| Bid Opening | 10/11/2024 | |
| Construction Advertisement Date | 9/18/2024 | |
| 100% Design Plans | 9/2/2024 | |
| 60% Design Plans | 7/19/2023 | |
| Design Notice to Proceed | 12/7/2022 | |
| Design Award | 11/3/2022 | |
| RLI Advertised | 7/19/2022 | |
| A/E Selection Process Start | 9/12/2022 | |
| A/E Shortlisting | 8/16/2022 | |
| A/E Presentations/Selection | 8/23/2022 | |
| A/E Fee Negotiation | 9/22/2022 |
Last Updated:
The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.
Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address, the content of your email, or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.
All content © 2026 Escambia County, FL and its representatives. All rights reserved.