South Old Corry Field Road Improvements (Bridge Replacement, Sidewalk, & Drainage)

As a result of the April 2014 flooding event, approximately 300' of Old Corry Field Road washed out above and on each side of the existing box culverts at East Jones Creek.

The County installed an open-bottom precast bridge to replace the damaged structure. 

Milestones

Milestone Date Notes

Last Updated:

BRIDGE REPLACEMENT, SIDEWALKS & DRAINAGE:

  • Construction Start Date: 10/8/18
  • Construction 100% Complete


   

  • Old%20Corry%20Field%20Road%20Aerial%20Map
  • Sidewalk area
  • Old%20Corry%20Field%20Before%20&%20After
  • Picture1
Project Manager:
Office Phone:
850-595-1625
Cell Phone:
850-516-2855
Architect/Engineer:
BRIDGE: Baskerville-Donovan & Contech Engineered Solutions SIDEWALKS: Jehle Engineering
Contractor:
ROADS INC.
District:
District 2
Funded:
Yes
Funding Sources:
L.O.S.T.
Sponsoring Division:
Engineering - Construction Management
Date Completed:
5/5/2020
Escambia Countuy Logo

The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.

Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.

All content © 2023 Escambia County, FL and its representatives. All rights reserved.