Gulf Beach Hwy Drainage Outfall at Sunset\Patton\Elite\Winthrop
The goal of the Gulf Beach Hwy Drainage Outfall at Sunset\Patton\Elite\Winthrop project is to design and construct a drainage system to replace an aging system located between Holmes Ave and Gulf Beach Highway. The current system was originally constructed in the late 1940’s and has begun deteriorating and could result in damage to the area. This new project will follow a similar footprint to the original system to ensure the areas current drainage needs are met. The proposed system will outfall around 7.5 acres from an inlet located from Elite Road and include inlets along Ellis Drive and Holmes Drive.
Milestones
Milestone | Date | Notes |
---|---|---|
A/E Selection Process Start | 8/24/2021 | RLI submitted to Purchasing for processing. |
A/E Shortlisting | 12/31/2021 | |
Design Award | 3/24/2022 | DRMP |
30% Design Plans | 5/5/2022 | |
60% Design Plans | 5/2/2022 | |
90% Design Plans | 12/16/2021 | |
100% Design Plans | 2/2/2024 | |
Property Acquisition | 3/29/2023 | |
Permit Acquisition | 2/7/2024 | |
Construction Advertisement Date | 4/16/2024 | |
Bid Opening | 5/16/2024 | |
Construction Award | 8/1/2024 | |
Construction Notice to Proceed | 10/16/2024 | |
Construction 25% Complete | 1/15/2025 | |
Construction 50% Complete | 3/13/2025 | |
Construction 75% Complete | 6/13/2025 | |
Construction Final Completion | ANTICIPATED: AUGUST 2025 (NAVY UTILITY CONFLICTS) | |
Warranty Completion/Warranty Dates | To Be Determined |
Last Updated: 6/18/2025
Project Manager:
Office Phone:
850-595-3562
Cell Phone:
850-554-3061
Architect/Engineer:
DRMP
Contractor:
Site & Utility
District:
District 2
Funded:
Yes
Funding Sources:
L.O.S.T.
Sponsoring Division:
Engineering - Construction Management