Dallas Avenue Drainage Improvements

The Dallas Avenue Drainage Improvements project, located between Bellview Avenue and Seattle Avenue, consists of the following:

  • Installation of 1126 feet of a 36 inch drainage pipe; 
  • Installation of 151 feet of an 18 inch drainage pipe;
  • Installation of 15 inlets along Dallas Avenue;
  • Reconstruction of the Dallas Avenue at Tupelo Avenue intersection;
  • Installation of approximately 1245 feet of a 6” water line
  • Replacing sidewalk; and
  • Installation of a new fire hydrant.

Milestones

Milestone Date Notes

Last Updated:

  • Construction Completed: January 2018 - March 2018
  • Aerial Photo
  • Streetview
Project Manager:
Office Phone:
850-595-3443
Architect/Engineer:
Ken Horne & Associates
Contractor:
Allsouth Construction Services, LLC
District:
District 1
Funded:
Yes
Funding Sources:
L.O.S.T.
Sponsoring Division:
Engineering - Construction Management
Date Completed:
3/31/2018
Escambia Countuy Logo

The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.

Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.

All content © 2023 Escambia County, FL and its representatives. All rights reserved.