Milestone | Date | Notes |
---|---|---|
Warranty Completion/Warranty Dates | MARCH 2023 - MARCH 2026 | |
Construction Final Completion | 6/13/2022 | |
Construction 75% Complete | 5/5/2022 | |
Construction 50% Complete | 4/8/2022 | |
Construction 25% Complete | 2/15/2022 | |
Construction Notice to Proceed | 9/15/2021 | |
Construction Award | 4/22/2021 | |
Bid Opening | 3/24/2021 | |
Construction Advertisement Date | 2/22/2021 | |
Permit Acquisition | 2/4/2021 | |
Property Acquisition | 2/4/2021 | |
100% Design Plans | 4/6/2020 | CSX Permit & Easement presented at the January 21, 2021 BCC meeting. |
90% Design Plans | 6/8/2017 | Kingsfield at 297-A (on same contract) was prioritized to be completed ahead of CR 95 at Old Chemstrand. |
60% Design Plans | 1/6/2017 | |
Design Notice to Proceed | 11/16/2016 | |
Design Award | 11/3/2016 | |
A/E Fee Negotiation | 10/17/2016 | |
A/E Presentations/Selection | 9/20/2016 | |
A/E Shortlisting | 9/13/2016 | |
RLI Advertised | 8/22/2016 | |
A/E Selection Process Start | 7/11/2016 | |
BCC Project Approval | 11/3/2016 |
Last Updated:
The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.
Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.