The County Road 164 Widening project located in District 5 will expand the existing lane width of approximately 8.5 feet to a proposed width of 11 feet on both sides of the roadway. There are two locations along County Road 164 included in this project with modifications totaling 11,420 linear feet. The first and westernmost section begins at State Road 97 and extends 3,600 linear feet eastward. The second location on the east side is centered on North Pine Barren Road and extends east and west for a total length of 3,960 linear feet.
The roadway will be overlain with two inches of asphalt. Existing striping orientations shall be followed with the new striping. Roadside shoulders and front slope will be sodded with Bahia sod and other disturbed areas will be seeded and mulched as needed.
Projected construction costs total $1,254,956.
Milestone | Date | Notes |
---|---|---|
Warranty Completion/Warranty Dates | 11/1/2024 | - 10/31/2026 |
Construction 25% Complete | 8/21/2024 | |
Construction Final Completion | 10/31/2024 | |
Construction Notice to Proceed | 6/17/2024 | |
Bid Opening | 4/2/2024 | |
Construction Advertisement Date | 2/29/2024 | |
BCC Project Approval New | 8/3/2023 |
Last Updated:
The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.
Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.