Chandler Street Drainage Improvements

This project will improve drainage conditions within the evaluation area. Drainage improvements will be designed for placement within the right-of-way of Chandler Street and Chauncey Street, east of Chandler Street and across the Burlington Northern Railroad Track for connection to the Holsberry Regional Retention Pond. Project Design was completed in August 2023 and Construction completion is anticipated August 2024, pending weather.

Milestones

Milestone Date Notes
100% Design Plans ANTICIPATED: JUNE 2024
60% Design Plans 7/19/2023  
Design Notice to Proceed 12/7/2022
Design Award 11/3/2022
RLI Advertised 7/19/2022
A/E Selection Process Start 9/12/2022
A/E Shortlisting 8/16/2022
A/E Presentations/Selection 8/23/2022
A/E Fee Negotiation 9/22/2022

Last Updated:

  • Chandler 2 photo
  • Chandler photo
  • Aerial Map of Project Area
Project Manager:
Office Phone:
850-595-3443
Architect/Engineer:
Waggoner Engineering
Contractor:
To Be Determined
District:
District 5
Funded:
Yes
Funding Sources:
L.O.S.T.
Sponsoring Division:
Engineering - Construction Management
Escambia Countuy Logo

The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.

Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.

All content © 2023 Escambia County, FL and its representatives. All rights reserved.