Given the extent of damage in this area, Escambia County completed the Blue Springs at Clearwater Long Term Drainage Analysis to address drainage deficiencies in the area East of Crescent Lake to determine the best approach for funding drainage improvements to provide for future sustainability for the area, and mitigate such drainage impacts from future occurrence. Six potential stormwater improvements were evaluated to reduce the potential for flooding in the area. Two of the options were referred to FDOT for consideration to make improvements to the Empire Pit. Four alternatives were evaluated to provide stormwater attenuation and treatment for the upstream basin, contributing to Blue Springs Avenue, in the area of Sun Valley Drive, Glass Drive, Clearwater Avenue. The recommended alternative is to maximize the pond stormwater volume, depending upon successful property acquisition. The recommended solution can be found in the figure below.
Milestone | Date | Notes |
---|---|---|
Warranty Completion/Warranty Dates | 2/25/2021 to 2/25/2023 | |
Construction Final Completion | 2/25/2021 | |
Construction 75% Complete | 12/20/2021 | Substantial Completion: 1/25/21 Final Expected: 2/25/21 |
Construction 50% Complete | 11/4/2020 | |
Construction 25% Complete | 10/10/2020 | |
Construction Notice to Proceed | 8/3/2020 | |
Construction Award | 5/29/2020 | |
Bid Opening | 5/1/2020 | |
Construction Advertisement Date | 4/24/2020 | |
Permit Acquisition | 3/10/2020 | |
Property Acquisition | 8/19/2019 | |
100% Design Plans | 11/25/2019 | |
60% Design Plans | 9/11/2019 | |
30% Design Plans | 7/7/2019 | |
Design Notice to Proceed | 4/16/2018 | |
Design Award | 4/13/2018 | |
A/E Fee Negotiation | 2/8/2018 | |
A/E Presentations/Selection | 1/5/2018 | |
A/E Shortlisting | 1/3/2018 | |
A/E Selection Process Start | 10/13/2017 |
Last Updated:
The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.
Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.