Phase 1: Construction from Gregg Road to Yancey Avenue: Complete
Phase 2: Construction from Yancey Avenue to Johnson Avenue Realignment
Milestone | Date | Notes |
---|---|---|
Warranty Completion/Warranty Dates | 3/15/2021 to 3/15/2023 | |
Construction Final Completion | 3/15/2021 | |
Construction 75% Complete | 3/30/2020 | |
Construction 50% Complete | 5/30/2019 | |
Construction 25% Complete | 12/30/2018 | |
Construction Notice to Proceed | 5/14/2018 | |
Construction Award | 3/15/2018 | |
Bid Opening | 2/14/2018 | |
Construction Advertisement Date | 1/15/2018 | |
Permit Acquisition | 7/11/2018 | Substantial Completion: January 28, 2021 |
Property Acquisition | 2/2/2017 | |
100% Design Plans | 9/6/2017 | |
90% Design Plans | 8/24/2017 | |
Design Notice to Proceed | 10/24/2011 | Phase 2 |
Last Updated:
The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.
Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.