Myrtle Grove Elementary Pond
The Myrtle Grove Elementary Pond Design is a stormwater routing and retention project designed to alleviate chronic flooding issues at Myrtle Grove Elementary School.
The pond design will include a pop-off or emergency overflow route running west through a series of ponds/easements before eventually out letting into the stormwater system previously constructed with the Myrtle Grove Sidewalk Project along 65th Avenue.
Scope to include pond siting, real estate acquisition, stormwater and pond design and construction.
Last Updated: 4/25/2025
- Real Estate Acquisition: Underway: August - January 2019
- 2 willing property owners
- Closed on 1 property acquisition January 17, 2019
- Scope Received & Re-Design Pending
- Construction Anticipated: PENDING: Real Estate Acquisition
- 2 willing property owners