Permitting Availability
“Take” is defined as the loss of designated critical habitat, measured in acres. Per the HCP, take allotments occur on a 5-year cycle and are determined by zoning category. Once the allotted take for each category is expended, no additional permits may be issued until the following permit cycle.
Current Cycle: 2020-2025
Zoning Category |
Take Remaining (ac) |
R-1 PK (LDR) |
0.0 |
R-2 PK (MDR) |
.092 |
R-3 PK (HDR) |
1.70 |
PR-PK |
7.42 |
C-1 PK |
1.02 |
CC-PK |
1.92 |
For inquiries on take availability or specific parcels, contact our office.