Title Goes Here

Myrtle Grove Elementary Pond

The Myrtle Grove Elementary Pond Design is a stormwater routing and retention project designed to alleviate chronic flooding issues  at Myrtle Grove Elementary School.

The pond design will include a pop-off or emergency overflow route running west through a series of ponds/easements before eventually outletting into the stormwater system along 65th Avenue previously constructed with the Myrtle Grove Sidewalk Project. Scope to include pond siting, real estate acquisition, stormwater and pond design and construction.

  • Surveying & Subsurface Utility Engineering (SUE) Complete
  • Real Estate Acquisition: Underway
  • 30% Plan with School Approval Complete
  • 60% Design: Submitted October 2017
  • Construction Anticipated: April - September 2018
  • PENDING: Real Estate Acquisition

  • 3_6
  • drainage%20route%20prelim%20Site%20

Last Updated: 11/01/2017

Project Manager:
TJ Williams

Email:
tjwilliams@myescambia.com
Office Phone:
850-595-3417
Architect/Engineer:
Sigma
Contractor:
TBD
District #:
District 2
CRA District:
Safe Neighborhood District:
Funded:
Yes
Funding Sources:
L.O.S.T.
Sponsoring Division:
Public Works - Engineering
Project Status:
Pre-Design
Funded via Local Option Sales Tax:
Yes

Plans

Related solicitations

Related continuing contracts

Tags