Upland Road Drainage Improvements

The Upland Road Drainage Improvements project consists of replacing single 30-inch reinforced concrete pipe with larger capacity pipes and installation of six inlet-junction boxes.

Milestones

Milestone Date Notes
Warranty Completion/Warranty Dates To Be Determined
Construction Final Completion ANTICIPATED: MARCH 2024
Construction 75% Complete 4/8/2024  
Construction 50% Complete 6/23/2023  
Construction 25% Complete 5/17/2023  
Construction Notice to Proceed 1/16/2023  
Construction Award 8/2/2022  
Bid Opening 7/8/2022
Construction Advertisement Date 6/8/2022  
100% Design Plans 5/31/2022

Last Updated:

  • Upland Road Project Photo
  • Upland Road Project Area Map
Project Manager:
Office Phone:
850-595-3738
Architect/Engineer:
Rebol-Battle
Contractor:
Quality Enterprises USA
District:
District 5
CRA District:
Cantonment
Safe Neighborhood District:
Cantonment
Funded:
Yes
Funding Sources:
FEMA
Sponsoring Division:
Engineering - Construction Management
Escambia Countuy Logo

The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.

Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.

All content © 2023 Escambia County, FL and its representatives. All rights reserved.