Surrey - Windsong Pond Drainage Improvements

The existing pond on Windsong Lane was constructed without a positive outfall built to the 100-year storage and 25-year conveyance standard requirements of today. 

This pond rehabilitation project will enhance storage capacity, provide positive outfall for the detention pond and provide an increased capacity to the stormwater conveyance system in order to reduce or eliminate flood risks to the surrounding neighborhood.

Milestones

Milestone Date Notes
Construction Final Completion 2/6/2024
Construction 75% Complete 12/8/2023 99% COMPLETE 01/25/24
Construction Notice to Proceed 9/20/2023
Bid Opening 7/27/2023  GPAD RFF / PANHANDLE
Construction Advertisement Date 7/12/2023  
Permit Acquisition 6/23/2023  
100% Design Plans 6/22/2023  
90% Design Plans 4/19/2023  
60% Design Plans 3/8/2023  
Design Notice to Proceed 4/28/2022
A/E Fee Negotiation 2/3/2022
A/E Presentations/Selection 1/5/2022
A/E Shortlisting 12/29/2021
A/E Selection Process Start 12/17/2021

Last Updated:

  • Surrey
  • map_surrey_windsong-concept2
Project Manager:
Office Phone:
850-595-3562
Cell Phone:
850-554-3061
Architect/Engineer:
Jacobs Engineering
Contractor:
To Be Determined
District:
District 1
Funded:
Design Only
Sponsoring Division:
Engineering - Construction Management
Date Completed:
2/6/2024
Escambia Countuy Logo

The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.

Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.

All content © 2023 Escambia County, FL and its representatives. All rights reserved.