The Southwest Greenway Parking Lot and Connector Trail 5th Extension project includes construction of a parking lot and connector trail for the Southwest Greenway Trail that is currently being designed and constructed.
The parking lot will be located on the south side of Inez Road, off of Fairfield Drive. The parking lot will consist of six all-weather spots and one handicap accessible spot. Approximately 500 feet of both surface trail and elevated board walk will be constructed to connect to the main trail.
Milestone | Date | Notes |
---|---|---|
Warranty Completion/Warranty Dates | 6/30/2022 | JUNE 30, 2022 - JUNE 30, 2024 |
Construction Final Completion | 6/30/2022 | To Be Determined |
Construction 75% Complete | 6/17/2022 |
|
Construction 50% Complete | 6/9/2022 |
|
Construction 25% Complete | 5/5/2022 |
|
Construction Notice to Proceed | 1/31/2022 |
|
Construction Award | 10/21/2021 |
|
100% Design Plans | 4/19/2021 |
|
90% Design Plans | 2/19/2021 |
|
30% Design Plans | 10/12/2020 | |
Design Notice to Proceed | 9/28/2020 | |
Design Award | 9/11/2020 | |
A/E Fee Negotiation | 8/21/2020 | |
A/E Presentations/Selection | 5/29/2020 | |
A/E Shortlisting | 5/28/2020 | |
A/E Selection Process Start | 5/15/2020 |
Last Updated:
The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.
Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.