Milestone | Date | Notes |
---|---|---|
Construction Award | 10/3/2024 | Site and Utilities |
Construction Final Completion | ANTICIPATED: APRIL 30, 2025 | |
Construction 75% Complete | 3/31/2025 | |
Construction 50% Complete | 2/28/2025 | |
Construction 25% Complete | 1/24/2025 | |
Construction Notice to Proceed | 12/2/2024 | |
Bid Opening | TO BE DETERMINED | |
100% Design Plans | 8/20/2024 | |
60% Design Plans | 6/21/2024 | |
Design Notice to Proceed | 4/22/2024 | |
Design Award | TO BE DETERMINED | |
A/E Shortlisting | 4/1/2024 | |
A/E Selection Process Start | 3/21/2024 | |
A/E Presentations/Selection | 8/15/2023 | PEA A/E NTP: 9/7/2023 PEA REPORT: NOVEMBER 2023 |
Last Updated:
The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.
Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.