The River Road Culvert & Walking Path Repair project consists of replacing the three existing 29” x 45” concrete culverts, headwalls, pedestrian bridge and associated asphalt roadway and asphalt paths that were damaged during Hurricane Sally. The project area is located approximately 2,040 linear feet north of the intersection of River Road with SR 292.
Full-depth reconstruction will be performed on the roadway directly above the culvert being replaced, with milling and resurfacing required within the immediate project area.
Milestone | Date | Notes |
---|---|---|
Warranty Completion/Warranty Dates | ANTICIPATED: APRIL 2024 - APRIL 2026 | |
Construction Final Completion | ANTICIPATED: APRIL 2024 | |
Construction 75% Complete | 1/31/2024 | |
Construction 50% Complete | 11/30/2023 | |
Construction 25% Complete | 10/31/2023 | |
Construction Notice to Proceed | 5/23/2023 | |
Construction Award | 11/3/2022 | |
Bid Opening | 9/27/2022 | |
Construction Advertisement Date | 8/25/2022 | |
Permit Acquisition | 3/1/2022 | |
100% Design Plans | 3/11/2022 | |
90% Design Plans | 10/27/2021 | |
60% Design Plans | 8/2/2021 | |
Design Notice to Proceed | 6/28/2021 | |
A/E Presentations/Selection | 3/26/2021 | |
Design Award | 6/28/2021 | |
A/E Fee Negotiation | 4/22/2021 | |
A/E Shortlisting | 3/26/2021 | |
A/E Selection Process Start | 1/27/2021 |
Last Updated:
The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.
Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.