The goal of this project is to reduce and redirect both stormwater and groundwater to prevent flooding at multiple locations within the Pine Valley Estates Subdivision. This includes the design of a new stormwater system along Dunaway Lane, Fridinger Drive, and Pursell Lane into an outfall at Eight-Mile Creek.
Milestone | Date | Notes |
---|---|---|
Warranty Completion/Warranty Dates | To Be Determined |
|
Construction Final Completion | 4/8/2024 | |
Construction 75% Complete | 8/11/2023 | |
Construction 50% Complete | 12/30/2022 | |
Construction 25% Complete | 10/28/2022 | |
Construction Notice to Proceed | 6/24/2022 | |
Construction Award | 5/5/2022 |
|
Bid Opening | 3/23/2022 |
|
Construction Advertisement Date | 2/7/2022 |
|
100% Design Plans | 9/1/2021 | |
90% Design Plans | 4/15/2021 | |
60% Design Plans | 12/22/2020 | Delayed due to Covid |
30% Design Plans | 10/12/2020 | |
Design Notice to Proceed | 7/13/2020 | |
Design Award | 5/5/2020 | |
A/E Fee Negotiation | 5/12/2020 | |
A/E Presentations/Selection | 4/23/2020 | |
A/E Shortlisting | 4/13/2020 | |
RLI Advertised | 3/23/2020 | |
A/E Selection Process Start | 3/17/2020 |
Last Updated:
The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.
Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.