Perdido Key is a barrier island which is part of the Gulf Islands National Seashore chain of islands that stretches for hundreds of miles along the Intercoastal Waterway.
Two separate projects were undertaken by the Florida Department of Transportation to design a Multi-Use Path that extends from River Road to the Alabama/Florida State line along Perdido Key Drive, formerly State Road 292. The intent of the project was to construct an 8’ (concrete) multi-use path along the North side of Perdido Key Drive. The project was prompted by pedestrian related crashes and fatalities in recent years. Design contracts were initiated by FDOT in 2017 with subsequent contract amendments through 2019.
On November 6, 2019, Escambia County took ownership of Perdido Key Drive through a transfer agreement with FDOT from Gongora Drive to the Alabama State line. At the time of the ownership transfer, design and permitting were not completed. Design services are needed to finalize design, complete utility coordination and permitting prior to commencement of construction activities. The design assignment agreements would allow Escambia County to complete the Multi-Use Pathway and improve community safety.
The Perdido Key Drive Multi Use Path East project extended from River Road to the western boundary of Perdido Key State Park. The path is 4.26 miles in length and joins the western project segment at the State Park border. This project has an extensive wildlife mitigation program to protect critical habitat for endangered species.
Milestone | Date | Notes |
---|---|---|
Warranty Completion/Warranty Dates | 7/22/2024 | 7/22/24 - 7/21/26 |
Construction Final Completion | 7/22/2024 | |
Construction 50% Complete | 1/24/2024 | |
Construction 25% Complete | 10/27/2023 | |
Construction Notice to Proceed | 6/15/2023 | CONSTRUCTION 6/15/23 & CEI: 3/13/23 (DRMP) |
Construction Award | 4/6/2023 | Pre-Construction Meeting: 4/18/2023 |
Bid Opening | 11/9/2022 | RE-BID TO OPEN FEBRUARY 2023 |
Construction Advertisement Date | 9/13/2022 | RE-BID TO ADVERTISE JANUARY 2023 |
Permit Acquisition | 6/30/2021 | |
100% Design Plans | 9/30/2021 | |
90% Design Plans | 12/8/2020 | |
Design Notice to Proceed | 8/20/2020 | Permit Acquisition Anticipated: 11/29/2020 100% Design Plans Anticipated: 12/4/2020 |
Design Award | 6/18/2020 | |
A/E Fee Negotiation | 5/20/2020 | |
A/E Presentations/Selection | 5/14/2020 | |
A/E Shortlisting | 5/14/2020 | |
A/E Selection Process Start | 5/12/2020 | |
BCC Project Approval | 4/2/2020 | 30/60/90% Design Plans were completed by FDOT in 2018 |
Last Updated:
To view progress photos, go to https://mds.multivista.com
User Name: pkmultiuse@gmail.com
Password: Multiuse2023
The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.
Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.