The Old Corry Field Road Resurfacing project consisted of resurfacing and reconstruction of Old Corry Field Road from Barrancas Avenue to New Warrington Road, in District 2. The project included maintenance of traffic, stormwater pollution prevention, sod stabilization shoulder work, pavement striping including reflective pavement markers (RPM), and dewatering of the work area. The contractor maintained traffic flow with minimal delays. Two-way traffic remained open during all non-working hours. The project duration was 180 days.
Milestone | Date | Notes |
---|---|---|
Warranty Completion/Warranty Dates | 3/8/2024 | 3/8/24 - 3/7/26 |
Construction Final Completion | 3/8/2024 | |
Construction 75% Complete | 1/24/2024 | |
BCC Project Approval | 7/18/2023 | |
Construction Notice to Proceed | 9/11/2023 | |
Construction Award | 7/18/2023 | |
Bid Opening | 6/28/2023 | |
Construction Advertisement Date | 6/1/2023 |
Last Updated:
DIST | OLD CORRY FIELD ROAD | FROM | TO |
---|---|---|---|
2 | SECTION 1 | BARRANCAS AVE | S. BRIDGE APPROACH NEW PAVEMENT |
2 | SECTION 2 | N. BRIDGE APPROACH NEW PAVEMENT | NAVY BLVD |
2 | SECTION 3 | NAVY BLVD | JACKSON ST |
2 | SECTION 4 | JACKSON ST | NEW WARRINGTON RD |
The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.
Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.