Milestone | Date | Notes |
---|---|---|
Construction 75% Complete | 4/8/2024 | |
Construction 50% Complete | 8/23/2023 | |
Construction Final Completion | ANTICIPATED: JULY 2024 | |
Construction 25% Complete | 6/23/2023 | |
Construction Notice to Proceed | 11/21/2022 | |
Construction Award | 11/3/2022 | |
Bid Opening | 6/30/2022 | |
100% Design Plans | 6/6/2022 | |
60% Design Plans | 7/21/2021 | |
BCC Project Approval | 6/23/2021 | Public Involvement |
Design Notice to Proceed | 5/20/2021 | Kickoff Meeting |
Design Award | 4/8/2021 | |
A/E Presentations/Selection | 2/17/2021 | |
BCC Project Approval | Anticipated: 04/22/2021 | |
A/E Fee Negotiation | 3/19/2021 | |
Design Award | 2/25/2021 | Sigma Consulting |
A/E Shortlisting | 2/4/2021 |
Last Updated:
The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.
Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.