Project is the restoration of 10+ acres of historic wetlands within the Jones Creek floodplain. The area was cleared and filled by the U.S. Navy in the 1950’s to provide a clearway beyond the southern end of the airfield runway as a safety feature. Project will restore wetlands and wildlife habitat by excavating fill material associated with the former clearway. Project will include initial geotechnical survey of fill material. Findings shall be evaluated for material suitability for clean fill material. Project will also evaluate fill material prior to removal for potential contamination.
Milestones
Milestone | Date | Notes |
---|---|---|
Construction Notice to Proceed | 5/18/2023 | Notice to Proceed issued to Streamline Environmental, LLC. for floodplain restoration construction activities in Jones Swamp Floodplain. |
Construction 25% Complete | 8/31/2023 | Construction of the Jones Swamp Floodplain Restoration project has reached approximately 25% completion. |
Construction 50% Complete | 9/30/2023 | Construction activities are approximately 50% complete for Jones Swamp Floodplain Restoration Project. |
Construction 75% Complete | 12/31/2023 | 75% completion of construction activities in Jones Swamp Floodplain Restoration Project. |
Last Updated: 3/25/2024
- Environmental Assessments Report Completed
- Wetland Delineation Completed
- Surveys Completed
- Bid Package Completed
- Project Funding: Gulf Restoration Fund
- Construction 90% completed.
- Substantial Completion - March 2024