Green Hills Road Pipe Replacement

Due to the heavy stormwater from the April 2014 rain event, a sinkhole developed on Green Hills Road causing the pipe to become partially exposed and damaged. The area above the pipes has been temporarily repaired with a filler and roadway patch. Future work includes replacement of the pipes due to sediment and debris blockage. Pipe failure is consistent with the sinkhole and erosion.

Milestones

Milestone Date Notes

Last Updated:

  • Construction Underway
    • 100% Completed
    • Completion Date: October 2016
  • This project will be submitted to the Federal Emergency Management Agency (FEMA) for reimbursement.
    • Requested FEMA Deadline - May 1st, 2017
  • Road%20Dept%20Post%20Storm
  • greenhills%20damage%20map
  • Green%20Hills%20Before%20004%20(2)
  • Green%20Hills%20@%20Creek%20Pipe%20Culvert%202014-07-21%20(1)
Project Manager:
Office Phone:
850-595-0793
Cell Phone:
8503753442
Architect/Engineer:
Sigma
Contractor:
J Miller Construction
District:
District 5
Funded:
Yes
Sponsoring Division:
Engineering - Construction Management
Date Completed:
10/19/2016

Files

Escambia Countuy Logo

The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.

Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.

All content © 2023 Escambia County, FL and its representatives. All rights reserved.