The Ferry Pass Community Center project, located at 8800 North 9th Avenue in District 4, is an existing 8,000 SF +/- building on the site to be renovated into the proposed Community Center by Escambia County Facilities Management.
The Escambia County Construction Management Division will manage the site improvements around the existing building, including but not limited to, a new parking lot, stormwater attenuation and detention, landscaping, and lighting.
Milestone | Date | Notes |
---|---|---|
Warranty Completion/Warranty Dates | JANUARY 19, 2025 - JANUARY 19, 2027 | |
Warranty Completion/Warranty Dates | To Be Determined | |
Construction Final Completion | 1/19/2025 | |
Construction 75% Complete | 10/25/2024 | |
Construction 50% Complete | 9/23/2024 | |
Construction 25% Complete | 7/31/2024 | |
Construction Notice to Proceed | 6/12/2024 | |
Construction Award | 5/21/2024 | |
Bid Opening | 4/30/2024 | |
Construction Advertisement Date | 3/28/2024 | |
Permit Acquisition | 3/14/2024 | |
BCC Project Approval New | ||
100% Design Plans | 3/25/2024 | |
90% Design Plans | 11/17/2023 | |
60% Design Plans | 10/19/2023 | |
Property Acquisition | 3/9/2023 | |
Design Award | 4/6/2023 | |
A/E Fee Negotiation | 3/8/2023 | |
A/E Presentations/Selection | 1/23/2023 | |
A/E Shortlisting | 1/30/2023 | |
A/E Selection Process Start | 1/23/2023 | |
30% Design Plans | 6/29/2023 | |
Design Notice to Proceed | 4/26/2023 |
Last Updated:
The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.
Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.