Crescent Lakes Outfalls

The Crescent Lakes Outfall project consists of replacing six outfalls that collect storm water from the adjacent streets and discharge into Crescent Lake. The 2014 April rainstorm event resulted in flooding as a result of damaged and or undersized outfalls. The replacement outfalls will be designed to prevent future flooding along East Shore and West Shore Drives.

Milestones

Milestone Date Notes

Last Updated:

  • Construction completed in 2 Phases
    • Phase 1: Construction of outfalls E1, E3, W1, W2 and W3.
      • Phase 1 Construction Complete
    • Phase 2: Outfall E2 Construction (Cranbrook Avenue)
      • Outfall Construction Complete
      • Phase 2 Construction:Complete
  • This project will be submitted to the Federal Emergency Management Agency (FEMA) for funding reimbursement
    • Requested FEMA Deadline: July 29th, 2017
  • 1
  • 2
  • Crescent%20Lakes%20Outfalls%20location%20map
Project Manager:
Office Phone:
850-595-1625
Cell Phone:
850-516-2855
Architect/Engineer:
David Fitzpatrick
Contractor:
BKW - Phase 1 ~~~ TBD Phase 2
District:
District 1
Funded:
Yes
Funding Sources:
Federal Grant
Sponsoring Division:
Engineering - Construction Management
Date Completed:
5/7/2017

Files

Escambia Countuy Logo

The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.

Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.

All content © 2023 Escambia County, FL and its representatives. All rights reserved.