The Ashcraft Road Dirt Road Paving and Drainage Project included paving of the existing 1.24 mile dirt road in northwestern Escambia County, in the Bratt community.
Ashcraft Road connects County Highway 99 to Bratt Road. Utility relocations and new waterline were included with this contract.
Milestone | Date | Notes |
---|---|---|
Construction Final Completion | 5/28/2021 | |
Construction 75% Complete | 1/7/2021 | Substantial Completion: 4/13/2021 |
Construction 50% Complete | 11/6/2020 | |
Construction 25% Complete | 9/10/2020 | |
Construction Notice to Proceed | 7/15/2020 | |
Construction Award | 6/7/2020 | |
Bid Opening | 5/21/2020 | |
Permit Acquisition | 6/18/2020 | |
Property Acquisition | 8/29/2019 | |
100% Design Plans | 12/17/2019 | |
60% Design Plans | 10/24/2019 | |
30% Design Plans | 12/6/2018 | |
Design Notice to Proceed | 10/12/2018 |
Last Updated:
The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.
Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.