Almax Court and North 52nd

This project will make repairs that were the result  of damage caused by the 2014 April Rainfall and is broken down into two different sites: Almax Court & North 52nd.

  • Almax Court
    • The existing twelve & eighteen inch pipes under the roadway running north and south on 57th and Almax were damaged during the rainstorm. The eighteen inch pipe will be removed and replaced. The twelve inch pipe will be removed and upgraded to an eighteen inch pipe.
  • North 52nd
    • Damages to the culvert and headwall will be removed and repaired with in kind structures.

Milestones

Milestone Date Notes

Last Updated:

  • Construction underway through September 2016
    • 99% Completed
  • This project is to be funded by the Federal Emergency Management Agency
    • Requested FEMA Deadline - January 5th, 2017.
  • Almax%20Court%20&%2057nd
  • 52nd_2
  • 52nd_1
Project Manager:
Office Phone:
850-595-3416
Architect/Engineer:
Jerry W McGuire & Associates
Contractor:
Chavers Construction
District:
District 2
Funded:
Yes
Sponsoring Division:
Engineering - Construction Management
Date Completed:
9/30/2016

Files

Escambia Countuy Logo

The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.

Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.

All content © 2023 Escambia County, FL and its representatives. All rights reserved.