FDOT February 1, 2019 Escambia County Traffic Alert

Published Feb 1, 2019

FDOT

Contact: Tanya Branton, (850) 330-1599, [email protected]

ChipleyDrivers will encounter traffic disruptions on the following state roads in Escambia and Santa Rosa counties as crews perform construction and maintenance activities.

  • Hanks Road Bridge Replacement over Breastworks Creek - Construction activities are scheduled to begin the week of Feb. 4.  The roadway will be temporarily closed during construction.  Drivers on Hanks Road, west of the bridge, will be detoured to County Road (C.R.) 99 and C.R. 4.  Drivers east of the bridge will utilize Pine Barren Road.
  • U.S. 98 Pensacola Bay Bridge Replacement – Lane closures will take place from 8 p.m. to 5 a.m. Sunday, Feb. 3 through Sunday, Feb. 10:
    • U.S. 98 east and westbound from North 14th Avenue in Pensacola to just east of the Pensacola Bay Bridge in Gulf Breeze. 
    • North 17th Avenue in Pensacola between U.S. 98 and the CSX Railroad overpass (Graffiti Bridge).
  • U.S. 29 Widening from Interstate 10 (I-10) to U.S. 90A (Nine Mile Road) – The following traffic impacts will occur from 8 p.m. to 6 a.m. Sunday, Feb. 3 through Saturday, Feb. 9.
    • Nine Mile Road at the U.S. 29 Overpass: Alternating traffic shifts will direct all traffic onto the westbound or eastbound lanes as crews continue construction of the new northbound bridge deck. Nine Mile Road lane restrictions are Sunday through Friday.
    • U.S. 29 between I-10 and 9 1/2 Mile Road: Drainage and paving operations continue. Drivers can expect alternating lane closures Monday through Saturday.
  • U.S. 98 (Chase Street) Resurfacing from North Palafox Street to State Road (S.R.) 196 (Bayfront Parkway)- Weather permitting paving operations from I-110 to Bayfront Parkway will resume the week of Sunday, Feb. 3.  Lane closures will be in effect from 9 p.m. to 6 a.m. Sunday through Thursday. 
  • U.S. 98 (Lillian Highway) Resurfacing from the Perdido Bay Bridge to Dog Track Road– Drivers may encounter lane restrictions from the Perdido Bay Bridge to Dog Track Road as crews perform miscellaneous operations to complete the project. Lane closures will be in effect from 8 p.m. to 5:30 a.m. Monday, Feb. 4 through Sunday, Feb. 10. 
  • Ninth Avenue Manhole Repairs - The northbound outside lane on Ninth Avenue will be closed at Jackson Street from 8 p.m. Tuesday, Feb. 5 to 5 a.m. Wednesday, Feb. 6 as crews perform manhole repairs.
  • U.S. 98 (Garden Street) Asphalt Repairs- The westbound outside lane will be closed from C Street to D Street from 8 p.m. Tuesday, Feb. 5 to 5 a.m. Wednesday, Feb. 6 as crews perform asphalt repairs.
  • Crary Road Bridge Replacement over Pritchett Mill Creek- Crary Road is closed between Tedder Road and Byrneville Road as crews construct a bridge culvert.  Motorists will be detoured via C.R. 4 and Byrneville Road. The project is anticipated to be complete spring 2019.
  • Bratt Road Bridge Replacement over Canoe Creek - Bratt Road will continue to be closed near Canoe Creek. Drivers on Bratt Road, west of the bridge, will be detoured to Pine Barren Road and C.R. 4.  Drivers east of the bridge will be detoured east on Bratt Road.  The project is anticipated to be complete summer 2019. 

Santa Rosa County:

  • U.S. 98 Pensacola Bay Bridge Replacement – Lane closures will take place from 8 p.m. to 5 a.m. Sunday, Feb. 3 through Sunday, Feb. 10:
    • U.S. 98 east and westbound from North 14th Avenue in Pensacola to just east of the Pensacola Bay Bridge in Gulf Breeze. 
    • North 17th Avenue in Pensacola, between U.S. 98 and the CSX Railroad overpass (Graffiti Bridge).
  • S.R. 4 Routine Bridge Maintenance over Cold Water Creek - Drivers will encounter alternating east and westbound lane restrictions over Cold Water Creek, about three miles east of S.R. 89, from 8 a.m. to 5 p.m. Sunday, Feb. 3 and Monday, Feb. 4 as crews perform routine bridge maintenance.
  • I-10 Widening from Escambia Bay Bridge to Avalon Boulevard (S.R. 281/Exit 22) The following construction related traffic impacts are planned for Interstate 10 and Avalon Boulevard the week of Sunday, Feb. 3:
    • Work on the on-and-off ramps at the Interstate 10/Avalon Boulevard (State Road 281/Exit 22) interchange will require overnight closures Sunday, Feb. 3 through Tuesday, Feb. 5.  Crews will be milling and resurfacing the following ramps between 8 p.m. to 6 a.m.  
      • Sunday, Feb. 3, I-10 westbound off-ramp.
      • Monday, Feb. 4, I-10 eastbound off-ramp.
      • Tuesday, Feb. 5, I-10 eastbound on-ramp.
    • Alternating lane closures on Avalon Boulevard, near the I-10 interchange, from 8 p.m. to 6 a.m. Monday through Thursday as crews perform construction activities.
    • Alternating lane closures on I-10, from the Escambia Bay Bridge to east of S.R. 281, from 8 p.m. to 6 a.m. Sunday, Feb. 3 through Friday, Feb. 8 as crews work to widen the roadway. 
    • Drivers will encounter new traffic pattern(s) on I-10 east and westbound as crews reconstruct the inside and outside shoulders. This work will continue through spring 2019.
  • U.S. 98 Safety Improvements at Constitution Drive and Navarre School Road- There will be eastbound lane closures near Thresher Drive Sunday through Thursday from 8 p.m. to 5 a.m. as crews construct a right turn lane. 
    • Drainage work is underway at Newport Street and Thresher Drive. 
    • Construction activities continue from Sunrise Drive to east of Cotton Bay Lane. Lane Closures will be in effect Sunday through Thursday from 8 p.m. to 5:30 a.m. as crews perform concrete operations in the median. 

All activities are weather dependent and may be delayed or rescheduled in the event of inclement weather. Drivers are reminded to use caution, especially at night, when traveling through a work zone and to watch for construction workers and equipment entering and exiting the roadway. 

For more information visit the Florida Department of Transportation District Three on the web at www.nwflroads.com, follow us on Twitter @myfdot_nwfl, or like us on Facebook at www.facebook.com/MyFDOTNWFL.

Visit Us on Social Media

Escambia Countuy Logo

The mission of Escambia County government is to provide efficient, responsive services that enhance our quality of life, meet common needs and promote a safe and healthy community.

Under Florida law, IP addresses and both the content of emails and email addresses are public records. If you do not want your IP address and the content of your email or your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in person.

All content © 2023 Escambia County, FL and its representatives. All rights reserved.