Contact: Tanya Branton, (850) 330-1599, [email protected]
Chipley– Drivers will encounter traffic disruptions on the following state roads in Escambia and Santa Rosa counties as crews perform construction and maintenance activities.
Escambia County:
- U.S. 29 Widening from Interstate 10 (I-10) to U.S. 90 (Nine Mile Road) – Drivers traveling U.S. 29 and Nine Mile Road will encounter traffic pattern changes from 8 p.m. to 6 a.m. Sunday, July 15 through Saturday, July 21.
- Nine Mile Road at the U.S. 29 overpass: North and southbound traffic will be reduced to one lane in each direction. Alternating traffic shifts will direct all traffic onto the westbound or eastbound lanes as crews continue construction of the new center bridge deck. Nine Mile Road lane restrictions are Sunday through Friday.
- U.S. 29 between I-10 and 9 1/2 Mile Road: Alternating lane closures as crews continue drainage and paving operations. U.S. 29 lane restrictions are Monday through Saturday.
- Northbound traffic has been shifted onto the newly constructed bridge section as demolition efforts continue.
- Due to the increased vertical clearance of the new bridge, the on-ramp has been extended up to the entrances of Emerald Cuts Salon and the Unitarian Universalist Church. This temporary shift will affect access to businesses and residences on the east side of U.S. 29 between 9 Mile Road and 9 1/2 Mile Road. For the next two months, motorists seeking access to properties on the east side of U.S. 29 will utilize the northbound on-ramp. Only right turns will be permitted for vehicles exiting driveways from these properties between 9 Mile Road and 9 1/2 Mile Road.
- U.S. 29 Resurfacing between U.S. 90 and Muscogee Road – Paving operations continue between Muscogee Road and West 9 ½ Mile Road. Lane closures will be in effect from 8 p.m. to 6 a.m. Sunday, July 15 through Thursday, July 19.
- I-10 / U.S. 29 Interchange Improvements Phase I – The following traffic impacts are planned on I-10 and U.S. 29 near the interchange (Exits 10) from 8 p.m. to 6 a.m. Sunday, July 15 through Thursday, July 19.
- Alternating lane closures on I-10 east and westbound and U.S. 29 north and southbound.
- The U.S. 29 on-ramps to I-10 eastbound will be intermittently closed. Traffic will be detoured on U.S. 29 to access I-10 eastbound.
- Alternating lane closures on the I-10 westbound exit ramp to U.S. 29 north and south (Exit 10).
- U.S. 98 Pensacola Bay Bridge Replacement – Alternating lane closures on U.S. 98 east and westbound between 14th Avenue in Pensacola and Bay Bridge Drive in Gulf Breeze from 8 p.m. to 5 a.m. Sunday, July 15 through Thursday, July 19 as crews perform construction activities.
- Airport Boulevard from S.R. 291 (Davis Highway) to S.R. 289 (9th Avenue) – Intermittent lane closures between Davis Highway and 9th Avenue from 8 p.m. to 6 a.m. Sunday, July 15 through Thursday, July 19 as crews perform construction activities.
- S.R. 10A (Scenic Highway) Underground Utility Operations for Addison Drive – The northbound, left turn lane will be closed from 8 p.m. Monday, July 16 to 5 a.m. Tuesday, July 17 as crews relocate underground utilities.
- S.R. 10/U.S. 90A (Nine Mile Road) Widening from Pine Forest Road to U.S. 29 – Waring Road will be closed at Nine Mile Road from 7 a.m. Tuesday, July 17 through 5 p.m. Friday, July 20 to place drainage pipes across the roadway. Motorists are encouraged to seek alternative routes. Detour signs and variable message boards are in place to alert drivers of the temporary road closure and detour routes.
All activities are weather dependent and may be delayed or re-scheduled in the event of inclement weather. Drivers are reminded to use caution, especially at night, when traveling through a work zone and to watch for construction workers and equipment entering and exiting the roadway.
For more information visit the Florida Department of Transportation District Three on the web at www.nwflroads.com, follow us on Twitter @myfdot_nwfl, or like us on Facebook at www.facebook.com/MyFDOTNWFL.