Lake Charlene Sediment Capture

This project consists of evaluating drainage systems within the Warrington watershed to
confirm Best Management Practices (BMP) installation(s) specifically designed to capture and reduce pollutant loading prior to discharge into Lake Charlene.

Construction plans will be developed for the installation of the BMPs designed to capture/reduce sediments and pollutant loading.
  • Notice to Proceed: November 2017
  • Watershed Evaluation: November 2017
  • Surveys & Geotechnical Expected: December 2017
  • Design Expected: January – April 2018; pending PO and study completion

Last Updated: 11/01/2017

Project Manager:
Terri Berry

Email:
Terri_Berry@myescambia.com
Office Phone:
850-595-3421
Architect/Engineer:
Jehle-Halstead, Inc.
Contractor:
TBD
District #:
District 2
CRA District:
Warrington
Safe Neighborhood District:
Funded:
Yes
Funding Sources:
L.O.S.T.
Sponsoring Division:
None
Project Status:
Pre-Design
Funded via Local Option Sales Tax: